Biogas plant, Biotehdas Ltd, Oulu

We carried out all the piping and equipment installations: process equipment, piping, gas storeroom, slurry bags, piping bridges and service platform steel structures. We were also responsible for the production of the service platforms and piping. The prime contractor on the project was Watrec Ltd. and the end customer was Biotehdas Ltd. The installations were done during 2014 and 2015.

Biogas plant, Honkajoki

Piping and equipment installations at the Honkajoen biogas plant: process equipment installation and piping production and installation, production and installation of the steel structures for the piping bridges, and gas