Piping and equipment installations at the Honkajoen biogas plant: process equipment installation and piping production and installation, production and installation of the steel structures for the piping bridges, and gas storage installation. The prime contractor for the project, which was completed in 2014, was Watrec Ltd. and the end customer was Biotehdas Ltd.
Bioenergy heating plant, Turku
Piping and combustion gas flue installations, PED documentation and NDT check on the pipes. The order was from Renewa Ltd. and the end customer was Turku Energy: completed in 2015.